The Signal / Practice / November 4, 2026
What a site is worth partway through approval
An infill lot is worth $500,000 as raw land. In our illustrative model it is worth $884,130 a year before its building permit, $1,084,100 the day the permit issues, and $500,000 again if the application lapses. We show the costs, the odds and the waiting time behind each step.
- $500,000Raw land
- $514,307Filed
- $674,669Approved
- $884,130Final
- $1,084,100Permit
Key points
- Value moves at milestones. An illustrative infill site rises from $500,000 raw to about $884,000 a year before its permit and $1,084,100 at issuance, then falls back to $500,000 if the application lapses. We show the formula and every input.
- Residential appraisers seldom analyze the cases where zoning or entitlement changes the answer. The AQB keeps subdivision analysis outside residential credentials, reviewers have described the checkbox habit since 2014, and Fannie Mae calls the analysis straightforward.
- We matched 927,006 rows of California housing progress reports. In seven large cities, 31 to 75 percent of entitlements approved 2018 to 2022 had no later building permit on the same parcel. San Francisco lists 47,444 entitled units with no permit application filed.
- Fannie Mae requires a zoning class and a highest and best use conclusion from an appraiser and requires neither when a model values the home. Where the legal use of the land sets the price, a model built on house size and features should be wrong more often.
A question with a market price
Investors put a price on what a site may legally become. Appraisal reports and valuation models usually leave it out.
A site gains value as it moves from raw land toward a building permit, and investors pay for each step. Land banking companies buy approved lots, hold them for large homebuilders and report the return they earn each quarter. Developers pay for an option to buy a parcel once the city approves a rezoning. When a city council reverses an approval, a jury may put a dollar figure on the loss. Each of those is a price for the same thing: what a site is worth at one point along the approval path.
Lenders value collateral in two ways, and the approval path is missing from both. On a residential appraisal, the appraiser must state whether the present use is the highest and best use. The appraiser often checks yes and adds a template sentence. An automated valuation model is built from closed sales and tax records. Those records do not list an approval stage, a condition of approval or an expiration date. And Fannie Mae's rules for sending a loan to a model instead of an appraiser require no zoning check, while its rules for the appraisal do.34
To price each step, we take an invented infill site through four approval milestones and apply a formula we show in full. Then we fill in the inputs with evidence: what approval costs, how often projects fail, how an approval can be lost after it is won, and how long permits take in the cities that publish usable data. Every invented number is labeled as illustrative. We also ran two data sets of our own, California's housing progress reports and New York City's zoning board records, and we describe the method and the limits of each.

What USPAP requires
USPAP requires appraisers to explain the highest and best use conclusion, and the explanation is most often missing in the unusual cases
USPAP Standards Rule 1-3(b) requires the appraiser to form an opinion of highest and best use when one is needed for credible results. Standards Rule 2-2(a)(x) requires the appraiser to summarize the support and reasoning for that opinion in the report.2 The old appraisal form gave the answer one checkbox. UAD 3.6 replaces the checkbox with four fields, one per test, plus a comment field. Our SEL-2026-08 feature works through those four tests with a Dallas residual land model.
Fannie Mae says the analysis is usually easy. Its September 2026 Playbook says that for most residential mortgage appraisals the analysis "is straightforward because the HBU is typically the property's present residential use as improved," and that it "becomes more important when a property's value potential includes an alternative use."6 Its FAQ adds that present use and highest and best use are "separate determinations."7 An ordinary house on an ordinary lot passes all four tests. The problem cases are the exceptions: zoning has changed, the lot can be split, an accessory unit could be added, or the current use is legal but no longer matches the zoning.
Reviewers have written about the checkbox habit for years. Philip Spool wrote in 2014 that many residential appraisers "are content with checking the box 'yes'" and that one paragraph covers all four tests.10 Russell Barrows wrote in 2018 that the analysis is "more than just checking the appropriate box on the form," and that he has reviewed reports citing residential zoning in towns that have no zoning at all.11 Illinois disciplined one appraiser in 2002 for a report that "misrepresented the zoning of the subject property" and another who "merely gave the definition of Highest and Best Use without doing the necessary analysis."12 The Appraiser Qualifications Board keeps "subdivisions for which a development analysis/appraisal is necessary" outside the Licensed and Certified Residential scopes, and its required highest and best use coursework lists general topics and nothing on entitlement.1 The only training we found that prices a site partway through approval was a November 2025 Appraisal Institute litigation session.44
Legacy report
✓Present use is the highest and best useOne box. The reasoning is often just the definition.
Four tests, and where they turn
- 1Legally permissibleZoning class, legal nonconforming status, a pending rezoning, a lot-split right, an accessory unit allowance.
- 2Physically possibleLot size and shape, access, utilities, slope and floodplain.
- 3Financially feasibleWhether the alternative use returns more than it costs to reach, including the approval process itself.
- 4Maximally productiveWhether the alternative beats the present use by enough to justify the time and risk of getting there.
Where the evidence comes from
| Source | What it says | Year |
|---|---|---|
| Fannie Mae Playbook and FAQ | Analysis usually straightforward; present use and HBU are separate determinations | 2026 |
| AQB criteria | Subdivision development analysis sits outside residential credentials | 2026 |
| Working RE, Spool | Many residential appraisers check yes without the rationale | 2014 |
| NEREJ, Barrows | Reports cite zoning that does not exist; rezoned areas missed | 2018 |
| Illinois IDFPR | Two discipline cases: misrepresented zoning; definition without analysis | 2002 |
| Appraisal Institute litigation session | Staged entitlement modeling taught, as conference programming | 2025 |
Value moves at milestones
Value rises at each milestone because a risk is removed, and a lapse takes the whole gain back
Appraisers who value development sites usually start from the value of the site as fully entitled and deduct what remains: the cost still to be spent, the time still to run and a return on the money tied up. Thomas Jensen's article on appraising development sites explains that method for two end states, entitled and unentitled, and stops there.43 Real options research has priced the option to wait on land for decades. Laura Quigg found an average option premium of about 6 percent of intrinsic value across 2,700 Seattle land sales.42 That research prices a single timing option rather than separate approval stages. The published US sources we read stop at the two end states, so our model fills in the stages between them and shows every assumption.
Vi = Pi × (VE − Ci) × Di + (1 − Pi) × VR
At stage i, P is the chance of reaching full entitlement from that stage, VE is the value once entitled, C is the cost still to spend, and VR is the value as raw land. D is a discount for the years still to run at a required rate of return, applied to the entitled branch only. Money already spent is left out of the value. It is equity at risk for the owner or the lender, and the table reports it on its own line. If the application lapses, the site is worth VR again and that equity is lost.
The California-style preset uses an entitled value of $1,100,000, a raw value of $500,000, a 15 percent rate and three years from filing to permit. With the discount, the site is worth $514,307 the day the application is filed, $674,669 once the rezoning is approved, $884,130 when the final plat clears and its appeal period ends, and $1,084,100 at permit. Without the discount, the filing-stage figure rises to $665,000. Three years of waiting at 15 percent a year removes most of the filing premium. A site with a long wait ahead can be worth little more than raw land even when the odds of approval are decent.
Stage table, with and without discounting
| Stage | Odds | Cost to go | Years to run | Value, discounted | Value, undiscounted | Equity at risk |
|---|---|---|---|---|---|---|
| Raw land | $500,000 | $500,000 | $0 | |||
| Application filed | 55% | $300,000 | 3 | $514,307 | $665,000 | $20,000 |
| Rezoning or preliminary approval | 80% | $150,000 | 2 | $674,669 | $860,000 | $70,000 |
| Final plat or site plan, appeals expired | 95% | $60,000 | 1 | $884,130 | $1,013,000 | $140,000 |
| Building permit issued | 99% | $10,000 | 0 | $1,084,100 | $1,084,100 | $200,000 |
Odds rise at each milestone because each one removes a way to fail. In this model, the passage of time changes only the discount, which lowers value.
Public filings put a price on the later stages. Millrose Properties, the land banking company spun out of Lennar, reports a weighted average yield of 8.5 to 8.6 percent on about $6.4 billion of homesites that builders hold under option.28 Walton Global's public land banking fund targets 9 to 11.5 percent, with builders taking the lots two to four years out.29 Forestar's agreement with D.R. Horton lets Forestar sell undeveloped land back within about a year at carrying value plus a 16 percent annual return, a shorter and different risk.30 In the filings we read, builders put down option deposits of about 6 to 20 percent of the purchase price, and the most a builder can lose is the deposit.31 Those yields match the carrying cost of the last two stages in the model. They tell us little about the filing stage, where the odds, the cost and the timing are all still open.
The C in the formula
The largest costs are the ones the city keeps if it denies the application
The remaining cost is several layers of spending, paid at different times. Impact and development fees are the largest layer in the states that charge them. The Terner Center's study of seven California cities put total development fees at 6 to 18 percent of the median new-home price, with Fremont charging $35,000 per single-family house,32 and the Duncan Associates survey put California's average impact fee on a standard house at $31,014, roughly double Maryland's.33 A full environmental impact report adds $150,000 to $300,000 in consultant fees on top of a state filing fee of about $4,100. A by-right project, one that needs no discretionary approval, pays none of that.
Refund rules separate the layers. Building permit fees are commonly 75 to 90 percent refundable when a permit is canceled before work begins. In the codes we read, the city keeps rezoning and entitlement application fees when it denies the application, and plan check and environmental review fees are gone once the work is done. That is why the model reports money already spent as equity at risk and keeps it out of market value.
- Pre-application studiesTraffic, environmental, geotechnical, surveyBefore filingKept on denial
- Design professionalsArchitect, civil engineer, plannerBefore and duringKept on denial
- Application and processing feesRezoning, variance, plat, site planAt filingKept on denial
- Environmental reviewCEQA or SEPA study and consultant feesDuring reviewKept on denial
- Attorneys and expeditersHearings, conditions, appealsDuring reviewKept on denial
- Carrying costInterest, taxes and insurance while waitingEvery monthKept on denial
- Impact and development feesSchools, roads, parks, utilitiesAt permitDepends on city
- Utility connection chargesWater, sewer, powerAt permitDepends on city
- Plan check and building permit feesThe last layer, after entitlementAt permitMostly refundable
Sourced figures behind the layers
| Figure | Amount | Source |
|---|---|---|
| Development fees, seven California cities | 6% to 18% of median new-home price | Terner Center, 201832 |
| Single-family fees, Fremont | $35,000 per house | Terner Center, 201832 |
| California average impact fee, standard house | $31,014 | Duncan Associates survey, 201233 |
| Environmental impact report consultant fees | $150,000 to $300,000 | Practitioner range, California |
| Building permit fee refund if canceled before work | 75% to 90% | Municipal fee schedules reviewed |
Denial is rare, failure is common
Boards seldom deny on the record, so published approval rates overstate the odds of finishing
The best tracked program we found is Massachusetts Chapter 40B. Lynn Fisher's study followed 404 projects in 115 communities filed from 1999 to 2005. Local boards approved 81 percent and denied 19 percent. Developers appealed 90 percent of the denials, and 69 percent of those appeals produced a permit through a state ruling or a settlement. Roughly 90 percent of projects were approved in some form. By mid 2008 only 62 percent of the approved projects held a building permit.14
New York rezonings show the same pattern. The Citizens Budget Commission tracked 171 private rezoning applications filed from 2014 to 2017 and found 60 percent approved after a median of two and a half years. The rest were withdrawn, pending or denied, and the summary does not break those down.41 A 2026 working paper that priced a standard 20-unit project across 60 cities found the chance of approval within six months fell from 71 percent in 2000 to 44 percent in 2025.15 That figure measures speed within a six-month window, which differs from the chance of ever finishing.
Three adjustments stand between those rates and the P in the formula. Count withdrawals as failures, because an applicant who quits after two years has lost the same money as one who was denied. Scale the rate for how much discretion the subject city has compared with the city the rate came from. And match the window to the stage, because the odds of finishing from a filed application differ from the odds from an approved rezoning. The calculator presets start at 55 percent for a California-style discretionary site and 80 percent for a Texas-style by-right site. Both are assumptions to test against the evidence here.
Rates, with what each one measures
| Source | Rate | What it measures |
|---|---|---|
| Fisher, Chapter 40B14 | 81% approved locally; 62% of approved permitted by 2008 | Affordable override projects, Massachusetts, 1999 to 2005 |
| Citizens Budget Commission41 | 60% approved, median 2.5 years | Private NYC rezonings filed 2014 to 2017 |
| D'Amico, Soltas and Wang15 | 71% in 2000 to 44% in 2025 | Standard 20-unit project approved within six months, 60 cities |
| NYC Board of Standards and Appeals22 | 73.6% granted, 19.0% withdrawn, 3.3% denied | General variances since 1998, our query |
Our match of 927,006 rows
In seven large California cities, a third to three quarters of entitlements had no later building permit on the same parcel
California requires every jurisdiction to report each housing project's entitlement, building permit and completion dates to the state, and the state publishes the table.21 We downloaded all 927,006 rows for 2018 through 2025, kept rows with a single parcel number, took every entitlement approved from 2018 to 2022, and looked for a building permit on the same parcel in the same city dated on or after the approval. We wrote the matching code twice, separately, and both versions gave the same Los Angeles and San Diego results to the decimal.
Los Angeles matched 69.0% of 4,732 entitlement rows, with a median of 183 days from approval to permit. San Jose matched 25.2%. For Los Angeles, San Diego and Oakland the match rate is about the same whether the entitlements are two years old or seven. That suggests most of the unmatched projects did not go on to a permit, rather than needing more time. San Francisco and San Jose match far less often for recent years, so part of their gap is projects still working toward a permit. Even San Francisco's 2018 entitlements, with seven years to show a permit, matched only 54.3%.
A missing match has several possible causes. Parcels get new numbers when a subdivision map is recorded, our rule drops projects that span several parcels, and data entry practice varies by city. Fresno matched 89.8% with a median of 15 days, which looks like entitlements and permits entered on the same day, so we left it off the chart. Even so, the data shows that entitled and permitted are different statuses and that the gap between them can be measured.
Match rate by entitlement year, Los Angeles and San Francisco
| City | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 |
|---|---|---|---|---|---|---|
| Los Angeles | 69.8% (835) | 67.8% (953) | 66.0% (967) | 71.7% (1,072) | 69.6% (905) | 61.0% (861) |
| San Diego | 55.6% (81) | 56.2% (32) | 67.6% (37) | 53.6% (56) | 56.9% (51) | 63.8% (47) |
| Oakland | 63.9% (438) | 52.2% (437) | 50.0% (424) | 62.7% (426) | 55.3% (380) | 50.7% (347) |
| Sacramento | 28.0% (218) | 55.7% (244) | 53.6% (267) | 0.0% (346) | 65.5% (391) | 64.3% (283) |
| Long Beach | 66.7% (15) | 55.6% (9) | 64.5% (31) | 34.8% (23) | 53.3% (30) | 68.5% (89) |
| San Francisco | 54.3% (46) | 39.6% (48) | 27.3% (33) | 33.3% (54) | 17.9% (28) | 18.5% (27) |
| San Jose | 38.9% (18) | 25.0% (20) | 23.8% (21) | 35.3% (17) | 16.3% (43) | 6.2% (32) |
The 2023 column has at most two years of runway and is shown for the trend only.
San Francisco's planning department keeps its own count. Its mid-2026 pipeline report lists 75,853 units, of which 61,749 are entitled and 3,327 are under construction. Adding the department's two "no permit filed" categories gives 47,444 entitled units, 77 percent of the entitled stock, with no building permit application on file.20
- Entitled, no permit application filed: 47,444 (62.5%)
- Entitled, permit filed or issued, work yet to start: 10,978 (14.5%)
- Under construction: 3,327 (4.4%)
- Under review, entitlement pending: 14,104 (18.6%)
Pipeline table
| Stage | Units | Share |
|---|---|---|
| Entitled, no permit application filed | 47,444 | 62.5% |
| Entitled, permit filed or issued, work yet to start | 10,978 | 14.5% |
| Under construction | 3,327 | 4.4% |
| Under review, entitlement pending | 14,104 | 18.6% |
| Total | 75,853 | 100% |
Risk after approval
An approval can be reversed, tied up in court or allowed to expire, and the odds in the formula cover none of those
The clearest dollar figure for a reversal comes from Alabaster, Alabama. A jury found a parcel worth $3,532,849.19 immediately before the city rezoned it in December 2011 and $500,000 after, an 86 percent drop. The Eleventh Circuit affirmed the judgment in June 2021. The "before" figure was the developer's documented spending on the project, which the jury treated as the value lost.13 Most suits like this fail. The Alabaster developer won because the jury found the city acted unlawfully. When voters pass a referendum before the last discretionary approval, the developer usually has nothing to claim.
Litigation mostly adds time. Holland and Knight reviewed 498 California appellate CEQA decisions from 2013 to 2023. Agencies won 75 percent of appeals, 64 percent of the challenged projects were on infill sites, and a case typically ran four to five years.16 In the model, that goes into the years to run and the cost rather than the odds. Expiration is the third way to lose an approval. A California tentative map lapses 24 months after approval by default, and extensions are capped at ten years.40 In Texas, Chapter 245 freezes the rules that apply to a project at its first permit application, but a project that goes dormant can lose that protection, and many city site plans expire on their own schedule.39 The lapse row in the calculator covers all three.
- ReversalAlabaster, Alabama. Rezoned Dec. 5, 2011; jury value from $3.53 million to $500,000; affirmed June 21, 2021.13
- LitigationCEQA appeals. 498 decisions, agencies win 75%, four to five years typical, 64% of targets infill.16
- ExpirationCalifornia tentative maps. 24-month default life, extensions capped at ten years.40
- VestingTexas Chapter 245. Rules freeze at the first permit application; dormancy can end the freeze.39

Measured where the data allows
Entitlement time and permit time are measured separately, and few cities measure either in a way that allows comparison
In 2022 Miami-Dade County's auditor tried to compare its permit times with other large jurisdictions. Four responded with usable data, and the office concluded that a comparison "could not be conducted due to the inconsistent permit types and non-homogeneous data provided."17 We ran into the same problem in open data. New York's permit issuance table shows a median near zero days because the review time sits in a separate dataset. Austin's addition permits carry application dates from master permits filed decades earlier. So the charts below cover few cities, and each one states its method.
The most careful comparison we found is a March 2026 report by San Francisco's Budget and Legislative Analyst, which gathered department data from six cities and warned that each city presents its data differently.18 San Francisco's 280-day median includes entitlement time from before 2024. After the city began tracking the two stages separately, permits filed and issued from January 2024 through August 2025 took a median of 114 days, and the planning department's entitlement stage took about four months on its own. Denver and Washington report averages rather than medians, so the chart marks them differently. Austin, at 91 days, and San Diego, at 134, are the fastest.
- Median
- Average
Windows and notes by city
| City | Days | Statistic | Window | Note |
|---|---|---|---|---|
| San Francisco | 280 | median | Filed before Aug. 12, 2025, issued Jan. 1, 2024 to Aug. 12, 2025 | Includes entitlement time before 2024 |
| San Francisco, post-entitlement | 114 | median | Filed and issued Jan. 1, 2024 to Aug. 12, 2025 | Building permit stage only |
| Denver | 274 | average | Issued about Dec. 2024 to Dec. 2025 | |
| Seattle | 185 | median | Issued Jan. 1, 2024 to Oct. 6, 2025 | |
| San Diego | 134 | median | Issued Jan. 2025 to mid Dec. 2025 | |
| Washington, D.C. | 92.6 | average | Oct. 2024 to Sept. 2025 | |
| Austin | 91 | median | Issued Jan. 1, 2024 to Aug. 25, 2025 | Building permits |
The type of job matters as much as the city. Los Angeles publishes every permit with its application and issue dates, so we computed 2024 medians for one and two family work: 238 days for a new house, 129 for an addition and 20 for an alteration or repair.23 Discretionary review adds the most time. A study of 350 Los Angeles multifamily projects found that by-right projects reached permit in a median of 477 days, against 747 for projects that needed discretionary approval. Projects that required a full environmental impact report averaged 43 months to approval.19
- All one and two family permits
- Permits adding an ADU
Medians and counts
| Job type | Median days | Permits | ADU median days | ADU permits |
|---|---|---|---|---|
| New one or two family home | 238 | 3,309 | 211 | 1,887 |
| Addition | 129 | 5,013 | 168.5 | 1,861 |
| Alteration or repair | 20 | 32,541 | 106 | 2,411 |
Variances, historic review, ADUs
Boards grant most cases that reach a vote, and the cost is the year of waiting and the conditions attached
New York City's Board of Standards and Appeals publishes every case with its final outcome, which most permit systems leave out. For the general variance under section 72-21, 1,983 cases since 1998 ended 73.6% granted, 19.0% withdrawn, 4.1% dismissed and 3.3% denied. For section 73-622, the special permit to enlarge a one or two family house that no longer meets the zoning, 631 cases ended 94.5% granted and 1.1% denied.22 Cases filed since 2015 took a median of 497.5 days to a grant for the general variance and 358.5 days for the house enlargement. Withdrawn cases ran a median of 501 days before they were pulled, about the same as the grants, so an applicant who gives up tends to do it late.
Historic review shows the same pattern. Richmond, Virginia's Commission of Architectural Review decided 834 cases from 2018 through 2024 and denied 26, a 3.1 percent rate, while approval with conditions was the most common outcome in every year.25 New York's Landmarks Preservation Commission issued only 55 percent of its discretionary certificates within its own ten-day target in 2024, against 88 to 98 percent for its routine permit types.26 Accessory dwelling units show the gap between the deadline in the law and the time measured in the data. California gives cities 60 business days to act on an ADU application, about twelve weeks. San Diego's ADU permits issued in 2024 took a median of 258 days from application, and Los Angeles took 211 days for a new detached unit and 106 for a conversion.2324 Lot splits under SB 9 remain rare: Los Angeles had approved none of 28 applications by late 2022, while a few small suburbs approved most of theirs.27
- Granted
- Withdrawn
- Dismissed
- Denied
Outcomes and timelines
| Section | Cases | Granted | Withdrawn | Dismissed | Denied | Median days to grant, filed since 2015 |
|---|---|---|---|---|---|---|
| 72-21 | 1,983 | 73.6% | 19.0% | 4.1% | 3.3% | 497.5 (206 cases) |
| 73-622 | 631 | 94.5% | 3.3% | 1.1% | 1.1% | 358.5 (128 cases) |
Medians and counts
| City and cohort | Median days | Permits |
|---|---|---|
| San Diego, issued 2021 | 172.5 | 894 |
| San Diego, issued 2022 | 250 | 980 |
| San Diego, issued 2023 | 289 | 1,618 |
| San Diego, issued 2024 | 258 | 1,736 |
| Los Angeles 2024, ADU new build | 211 | 1,887 |
| Los Angeles 2024, ADU addition | 168.5 | 1,861 |
| Los Angeles 2024, ADU alteration | 106 | 2,411 |

For an appraiser or a reviewer looking at a planned addition, a conversion or a lot split, the evidence is consistent. Outright denial was uncommon at every board we measured, between 1 and 5 percent of cases. The cost is the six months to two years the process takes, the conditions attached to the approval, and the share of applicants who quit late. The deadline in the law is a poor guide to the actual wait.
Two paths, one checkpoint
Fannie Mae requires a zoning class and a highest and best use conclusion from an appraiser, and requires neither when a model values the home
Fannie Mae's Selling Guide requires the appraiser to report the specific zoning class and to say whether the property is a legal conforming use, a legal nonconforming use, an illegal use, or in an area with no zoning. It also states that Fannie Mae "will only purchase or securitize a loan that represents the highest and best use of the site as improved."3 Value acceptance is the program that replaces the appraisal with a model. Its eligibility rules list the loans that qualify and the ones that do not, and the list says nothing about zoning, nonconforming use, accessory units or highest and best use.4 Neither Fannie Mae nor Freddie Mac buys loans on vacant land or land development at all.58 So the zoning check is required on one path and absent from the other.
An automated valuation model is built from closed sales and property records. Dye and McMillen studied Chicago-area teardowns and found that once a house becomes a teardown candidate, its size and features stop explaining its price, because buyers are paying for the land. Teardown rates ran above 9 percent of the housing stock in Winnetka against about 3 percent in Chicago.34 For those houses, a model built on square footage and bedroom count uses the wrong variables, and those houses cluster by neighborhood. The one peer-reviewed study we found on Minneapolis's 2040 plan found it moved single-family prices about 3 to 5 percent. The change showed up in land value and began when the policy was announced, before adoption.35 A model built from past sales picks up a change like that late, and in cities where prices moved less it has little to pick up.
The model industry's own comment letters agree. We read five AVM-industry comment letters on the 2024 quality control rule in full. None mentions zoning, highest and best use, land value or teardowns, though HouseCanary asked regulators to require validation by property segment.37 Clear Capital's glossary lists "large acreage" among the traits that lower a confidence score.36 The rule itself defines a dwelling as a one to four unit residential structure and says nothing about land.38 Freddie Mac's appraisal guide requires at least one comparable with an accessory unit for a compliant ADU and two for a non-compliant one, and says that "to simply ignore the ADU due to lack of comparable sales is an unacceptable appraisal practice."9 Since 2015, Freddie Mac's collateral tool has shown a warning message when the appraiser reports that the present use is not the highest and best use.45 Each of those rules applies to the appraisal path. We found no published measurement of model error for teardowns, upzoned parcels or lot-split candidates, so this chapter describes how the error would arise rather than how large it is.
What each guide section says
| Section | Requirement |
|---|---|
| B4-1.3-04, Site section3 | Report the zoning class; state legal conforming, legal nonconforming, illegal or no zoning; improvements must represent the highest and best use as improved |
| B4-1.4-10, Value acceptance4 | Eligibility by loan purpose, occupancy, property type, LTV and price; zoning, nonconforming use, ADUs and highest and best use are absent |
| B2-3-01 and Freddie Mac 5601.258 | Vacant land and land development properties are ineligible for purchase |
| AVM rule, 89 FR 6453838 | Applies to models valuing a consumer's principal dwelling, a one to four unit residential structure |
The model, with every input open
Set the entitled value, the raw value, the odds and cost at each stage, and the years to run
Two presets load the illustrative inputs: a California-style discretionary track with three years to run and a Texas-style by-right track with nine months. Both use the same arithmetic. Odds must rise or hold from one stage to the next, cost and years must fall or hold, and the entitled value must be above the raw land value. When an input breaks a rule, the table keeps its last valid numbers and a message names the problem. Without JavaScript, the table shows the California preset: $514,307 at filing, $674,669 at approval, $884,130 at final plat and $1,084,100 at permit, with raw land at $500,000.
| Stage | Value | If it lapses here | Equity at risk |
|---|---|---|---|
| Raw land | $500,000 | ||
| Application filed | $514,307 | $500,000 | $20,000 |
| Rezoning or preliminary approval | $674,669 | $500,000 | $70,000 |
| Final plat or site plan, appeals expired | $884,130 | $500,000 | $140,000 |
| Building permit issued | $1,084,100 | $500,000 | $200,000 |
Texas-style preset, undiscounted: $772,000 at filing against $500,000 raw, with an entitled value of $900,000. The two presets differ only in their inputs, mainly odds and years.
Questions for the loan file
What to ask about a partially entitled site, and about a house whose value rests on a planned change
Items marked as requirements come from the guides cited. The rest are our suggestions, drawn from the evidence above.
- RequirementConfirm the zoning class and use status in the report. Legal conforming, legal nonconforming, illegal or no zoning, with the class named, and a highest and best use conclusion with its rationale.23
- RequirementTreat vacant land and land development collateral as outside GSE purchase rules. Value acceptance does not reach them, so the valuation rests on the appraisal and the sponsor's assumptions.45
- SuggestedName the stage. Filed, approved, final with appeals expired, or permitted, with the date of each and the body that granted it.
- SuggestedList every condition of approval with its deadline. A missed condition can cause the approval to lapse. Record the map or site plan expiration date and any extension already used.3940
- SuggestedAsk whether vesting is active. In Texas, the first permit application date and any dormancy; in California, the vesting tentative map and any later development agreement.39
- SuggestedSeparate spent money from value. An as-entitled value with the sponsor's spending added back is a cost basis, as the Alabaster jury's "before" figure was.13
- SuggestedPrice the next milestone. Ask which risk it removes, and how much the required return reduces the entitled value over the years still to run.
- SuggestedCheck for pending litigation and ballot measures. A referendum certified before the last discretionary approval can end a project with no compensation.16
For appraisers
- SuggestedWrite the four tests for the exception cases. A pending rezoning, a lot-split right, an ADU allowance or a nonconforming use each needs a paragraph of analysis.67
- SuggestedGive the ADU its comparables. One with an ADU for a compliant unit, two non-compliant ones for a non-compliant unit, per Freddie Mac.9
- SuggestedReport the permit status of any planned or completed change, with the application date, so the reader can allow for the months of waiting the data above describes.2223
Our development-site report shows an entitlement adjustment supported by before-and-after approval sales, and our Washington upzoning feature covers what a statewide rezoning does to comparable selection.
Method and limits
- Model. V = P × (entitled − cost to go) × discount + (1 − P) × raw, per stage. Presets are illustrative. The discount applies 1 ÷ (1 + rate) to the power of the years still to run, to the entitled branch only.
- California progress reports. HCD's Table A2 export, 927,006 rows, 2018 to 2025, downloaded Nov. 3, 2026. Rows with one parcel number; entitlements approved 2018 to 2022; earliest later building permit on the same jurisdiction and parcel. Fresno is reported in the text but left off the chart because its figures look like a data entry artifact. Two separate implementations of the match agree.21
- New York zoning board. Board of Standards and Appeals open data, cases since 1998, counted by final status; medians for cases filed since Jan. 1, 2015, in calendar days from filing to decision.22
- Los Angeles and San Diego permits. Medians in calendar days from application to issuance for permits issued in the year shown, with the job-type filters named in the captions. Elapsed days include time the file sat with the applicant.2324
- Six-city table. Reproduced from the Budget and Legislative Analyst's report with its own window and statistic for each city. It compares published figures and does not rank the cities.18
- Limits. A missing match in the California data does not prove the project failed. Approval rates from other programs need adjustment before they stand in for one site's odds. We found no published measures of model error on land-driven properties or of the share of entitlements that expire. Fee figures are from the cited studies and schedules and vary by city.
This article is general information, not legal or valuation advice. Images marked as illustrations are AI-generated and show no real property. The California, New York, Los Angeles and San Diego tables are The Signal's analysis of public data; every other figure is from the cited source. The model's presets are illustrative and do not describe any real site.
Sources
- Appraiser Qualifications Board, Real Property Appraiser Qualification Criteria (January 2026 edition)
- The Appraisal Foundation, Uniform Standards of Professional Appraisal Practice (2024 edition)
- Fannie Mae, Selling Guide B4-1.3-04, Site Section of the Appraisal Report (accessed Nov. 3, 2026)
- Fannie Mae, Selling Guide B4-1.4-10, Value Acceptance (Appraisal Waiver) (accessed Nov. 3, 2026)
- Fannie Mae, Selling Guide B2-3-01, General Property Eligibility (accessed Nov. 3, 2026)
- Fannie Mae, The Highest & Best Use Playbook, Uniform Appraisal Dataset 3.6 (September 2026)
- Fannie Mae, Highest and Best Use FAQs (September 2026)
- Freddie Mac, Accessory Dwelling Units fact sheet (February 2026)
- Freddie Mac, A Practical Guide to Appraising Accessory Dwelling Units (Sept. 9, 2026)
- Philip Spool, Highest and Best Use Analysis, Working RE (Summer 2014)
- Russell Barrows, Residential highest and best use pitfalls, New England Real Estate Journal (Feb. 9, 2018)
- Illinois Department of Financial and Professional Regulation, Real Estate Appraisal disciplinary actions, 2002 (2002)
- South Grande View Development Co. v. City of Alabaster, No. 18-14044 (11th Cir.) (June 21, 2021)
- Lynn Fisher, Chapter 40B Permitting and Litigation, Rappaport Institute policy brief (November 2008)
- D'Amico, Soltas and Wang, Where Is Housing Slow to Build, Princeton CEPS Working Paper 357 (September 2026)
- Holland & Knight, Why California Can't Build Reliable and Affordable Essential Projects (September 2026)
- Miami-Dade County Office of the Commission Auditor, Building Permit Process Report (Nov. 14, 2022)
- San Francisco Budget and Legislative Analyst, Post-Entitlement Permitting in San Francisco (March 5, 2026)
- California YIMBY, Dysfunctional Metropolis: Housing Permitting in Los Angeles (June 2023)
- San Francisco Planning, Housing Production and Development Pipeline, 2026 Q2 (July 2026)
- California HCD, Housing Element Annual Progress Report data by jurisdiction and year, Table A2 (downloaded Nov. 3, 2026)
- NYC Open Data, Board of Standards and Appeals Applications Status (queried Nov. 3, 2026)
- Los Angeles Department of Building and Safety, Building Permits Issued from 2020 to Present (queried Nov. 3, 2026)
- City of San Diego, Permit Approvals (ADU) layer (queried Nov. 3, 2026)
- City of Richmond, Commission of Architectural Review, 2024 annual report (February 2025)
- NYC Comptroller, Final letter report on the processing of permit applications by the Landmarks Preservation Commission (2025)
- Terner Center, SB 9 Turns One: Applications and Approvals (January 2023)
- Millrose Properties, second quarter 2026 results (Aug. 4, 2026)
- Walton Global, $250 million land banking fund offering (July 17, 2025)
- Forestar Group, Form 10-K for fiscal 2025 (Nov. 2025)
- Meritage Homes, Form 10-K for 2018 (Feb. 2019)
- Terner Center, It All Adds Up: The Cost of Housing Development Fees in Seven California Cities (March 2018)
- NAHB Eye on Housing, Home building impact fees: state averages (Duncan Associates survey) (Jan. 2014)
- Lincoln Institute of Land Policy, Teardowns (Dye and McMillen) (2007)
- Daniel Kuhlmann, Upzoning and Single-Family Housing Prices, Journal of the American Planning Association 87(3) (2021)
- Clear Capital, AVM Testing: A Short Glossary (accessed Nov. 3, 2026)
- HouseCanary, comment letter on Quality Control Standards for Automated Valuation Models (July 26, 2023)
- Federal Register, Quality Control Standards for Automated Valuation Models, final rule, 89 FR 64538 (Aug. 7, 2024)
- Texas Local Government Code, Chapter 245, Issuance of Local Permits (accessed Nov. 3, 2026)
- California Government Code section 66452.6, tentative map expiration (accessed Nov. 3, 2026)
- Citizens Budget Commission study of private rezoning applications, reported by The Real Deal (Sept. 7, 2022)
- Laura Quigg, Empirical Testing of Real Option-Pricing Models, Journal of Finance 48(2) (1993)
- Thomas Jensen, Appraising Development Sites: With and Without Entitlements, New England Real Estate Journal (2019)
- Appraisal Institute Litigation Conference, Land Use Issues Affecting Valuation (SCCAI) (November 2025)
- Valuation Review, Freddie announces appraisal changes to the UCDP (message FRE1095) (April 29, 2015)
The Signal / Twice-monthly briefing
Get the next data feature in The Signal.
One sourced briefing, twice a month.
Unsubscribe in one click. We don't sell your email or share it with sponsors. Privacy Policy
